Aspen Heights, Jan. 12, 2023.

Broken Promises: Aspen Heights’ awaited move-in canceled for many disappointed students

GABRIELLE BOWMAN, Evergreen news co-editor February 27, 2023

Aspen Heights management sent out lease terminations on Feb. 20, informing several residents that they will not be moving into the apartments they were once promised.  Certain residents had already...

Aspen Heights, Jan. 12, 2023.

Time is Ticking: Students continue to be ghosted by Aspen Heights

GABRIELLE BOWMAN, Evergreen news co-editor January 13, 2023

Students are still awaiting entry to their apartments at Aspen Heights as of Thursday.  Aspen Heights promised its residents that move-in dates would happen in the fall semester 2022, however, just...

For students who are currently living in The Ruckus Student Living or the Yugo Pullman Hills, their move-in date is still undecided.

Displaced in December: Aspen Heights proposes new move-in dates

CHLOE EKSTROM, Evergreen reporter December 1, 2022

Students have not heard from Aspen Heights Pullman since Oct. 25 despite promises that students could move in at the end of November. It has been nearly four months since residents were displaced.  Residents...

Exterior construction on Aspen Heights units still needs finishing.

Aspen Heights further delays move-in

JOSIAH PIKE, Evergreen news co-editor November 3, 2022

Aspen Heights Pullman aims to let some residents move in by the end of November, which is three months after their initial move-in date.  “I don’t know whether that means one dwelling or six...

The Terre View roundabout is finished ahead of schedule, while the Albion road roundabout continues to see delays

Albion road roundabout construction behind schedule

PUNEET BSANTI, Deputy news editor August 23, 2022

The construction of the second roundabout located at North Grand Avenue and Albion Road is running behind schedule. The roundabout is being built by Aspen Heights in order to accommodate increased traffic...

Construction on the Aspen Heights complex will continue until mid-October, then students may be able to move into their apartments.

OPINION: Aspen Heights’ communication errors unacceptable, displace WSU students

ANNABELLE PEPIN, Evergreen columnist August 18, 2022

Eager to live independently in a new place, a significant number of WSU Pullman students were scheduled to move into Aspen Heights’ off-campus cottages on Aug. 13. However, with new developments comes...